Weatherchem Corporation

Twinsburg, OH

2015

Emergency build for blown transformer. Added a new addition for switchgear to replace failed existing service

2013
A 2,000 square foot addition to current plant

2009
Complete remodel of the plant interior for production

Challenge

 Weatherchem had an underground power line fail and blow out the existing switchgear. 

Solution

 We were able to contact the building department and move forward under an emergency situation to build an new room ofr the new electrical equipment. With expedited equipment deliveries we were able to replace the existing equipment within weeks of the failure.