McCann Plastics

 20,000 sqft precast concrete addition to and existing facility in Green, OH.  Completed 2015

Challenge

 The client bought the existing facility before contacting our firm. They needed to expand the facility to maximize its use for future production and storage. The existing site had issues with a stormline and existing gas well easement that made it difficult to expand the facility.

Solution

 AS a design/build contractor we were able to work with our engineers and architect to develop a plan to move the existing storm line and still give access to the existing easement. This allowed the project to double its current facility and gain 3 additional loading docks for shipping and revceiving.